City of St. Helena

 

 

Napa River Flood Protection Project

Performance-Based

Operation & Maintenance Manual

For the

Enhanced Minimum Plan

(Adaptive Management Plan)

 

 

 

 

 

 

 

DRAFT

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Prepared by:

City of St. Helena

1480 Main Street

St. Helena, California 94574

(707) 967-2792

Myke Praul, City Engineer

July December 2003

 

 

INTRODUCTION

 

The St. Helena Comprehensive Flood Protection Study has analyzed a number of project alternatives, which are described in the Draft St. Helena Feasibility Study (MBK Engineers, 2002) and the Revised Draft Environmental Impact Report (CDM, MBK, MIG, July August 2003).  From this study and at this point of time, the community has identified the Enhanced Minimum Plan as both the preferred alternative and the environmentally superior alternative.  Although the final design has not been completed, the construction features of the Enhanced Minimum Plan will likely include the following:

·         The creation of terraces on the left (east) bank of the Napa River across from and upstream of VVMHP, as well as the creation of a terrace on the right (west) bank of the river within VVMHP and upstream to Adams Street. These terraces would vary from about 100 to 300 feet in width and would extend from about 0 to 10 feet in depth. 

·         The removal of under story and lower canopy vegetation on the existing left bank terrace of the Napa River, opposite of the Sulphur Creek confluence. The removal of this vegetation will improve channel conveyance in this section of the river.

·         Construction of a new levee/floodwall along the right bank terrace within VVMHP and upstream to Adams Street. This floodwall is an inverted T-type cantilever wall with a concrete keyway/cutoff. The length of the wall is approximately 925 feet. The height of this varies from 2 feet near Sulphur Creek to about 6 feet near Redondo Court in the VVMHP.

·         The relocation of up to 33 spaces from VVMHP. The relocation of units in the VVMHP will be required to accommodate the proposed right side terrace and floodwall. These homes will be relocated to new spaces created along and to the north of Del Rio and Del Campo Courts.

·         The extension of Adams Street from its existing terminus to Paseo Grande in the first phase, and eventually, to the Silverado Trail. This extension would be built on top of a levee and would lengthen Adams Street by approximately 3,500 feet when fully constructed.  Beyond Paseo Grande, a levee would be built to the edge of Terrace B.  This will provide flood control protection for the VVMHP and areas to the south.  Once additional environmental review is completed, the Adams Street extension and causeway would be built on top of the levee.   A new bridge structure will provide access across the Napa River and terraces adjacent to the river channel, with the roadway at a minimum elevation of 3 feet above the 100-year water level in the river. 

·         Extension of Paseo Grande from its current terminus northwest to connect with Adams Street.  The intersection of Adams St. and Paseo Grande would be gated and closed to all through traffic except emergency vehicles. 

·         Modification of the existing storm drains in and/or along Del Rio Court.

·         Construction of a levee or a floodwall to protect the operations buildings at the City Wastewater Treatment Plant. This feature will have a top elevation of 204 feet, or 5 to 6 feet above the finished grade. At this height, the floodwall will be 3 feet above the calculated 100-year water surface elevation at the treatment plant.

·         Removal of existing riprap on the “point” of the west bank of VVMHP.  This stretch of riverbank will likely require a bio-engineered bank protection feature.

·         Installation of large woody debris and or rootwads as part of a streambank repair project on Sulphur Creek at the confluence with the Napa River.  These measures will enhance stream habitat and provide protection for fish migration through this reach of the creek.

·         Enhancement of the river channel for fish passage through the Pope Street Bridge reach by removing the Pope Street sill.

 

The overall goal of the maintenance and adaptive management plan is to achieve the project’s objectives after construction and well into the future.

 

The framework for this Adaptive Management Plan can be found in the report prepared by Swanson Hydrology & Geomorphology entitled Geomorphic Design Report, January 6, 2003.  Adaptive management is by definition the linking of new data to actions and measures in order to achieve the overall project goals. The post-construction period will involve an initially intensive effort to establish the desired vegetation communities in the excavated areas. As described in the proposed project features listed above, it is anticipated that the overbank areas would be planted prior to exposure to floods in order to establish a stable plant community that will hold soil.

 

Many details of the construction and planting plan will be developed in subsequent engineering, design and construction phases.  Meeting and maintaining conditions consistent with the project goals will require long-term monitoring, some maintenance (although it is a stated objective to minimize maintenance and have a self-sustaining ecosystem), and structural modifications to respond to changing conditions. Any proposed structural modification will involve a planning process to ensure that input of resource agencies and the community is incorporated into the design of any needed remedial measures.  The Adaptive Management Plan provides the framework for this ongoing process.

 

An annual monitoring report will be produced to include the data, results, recommendations for any remedial actions, and proposed modifications to the project features or monitoring procedures. The monitoring team will consist of the City Engineer, a hydrologist/geomorphologist, a representative from the Department of Fish & Game, the city’ arborist and the maintenance representative of the City of St Helena. The annual report will be circulated to the appropriate resource agencies, and made available to the community and other stakeholder members for review. Annual recommendations shall be supported by a record of decision and made available for public review.

 

Based upon the proposed structural modifications with the EMP, the main areas of maintenance concern are as follows:

 

1) Vegetation planting success.

2) Topographic Changes in the Channel and created overbank areas.

3) Hydraulic performance of the project to pass various flows, including evaluation of existing vegetation maintained annually.

4) Erosion monitoring to address problems threatening infrastructure or properties designated for protection.

5) Aquatic and biotic resource conditions.

 

 

PERFORMANCE BASED APPROACH

 

The objectives of a performance based O & M manual are to:

 

·        Assess hydraulic performance of project features;

 

·        Monitor sediment deposition and aggradations in the Project Reach.

 

·        Monitor streambank stability; and

 

·        Monitor existing and proposed vegetation for success of riparian habitat and flood conveyance roughness coefficients; and

 

·        Monitor the success of ecosystem restoration by documenting aquatic and other wildlife populations in the project reach over time.

 

The Napa River in the reach of the flood protection project is very dynamic with a substantial slope.  Changes in the physical features of the natural and improved channel can change periodically.  These changes may be allowed to occur without any maintenance requirements as long as they do not adversely affect the Project’s hydraulic performance or the stability, structural integrity and habitat quality within the Project reach.  Hydraulic performance will be assessed through monitoring of physical features and the use of a hydraulic model.  Streambank stability will be assessed using repeated cross section surveys, erosion pins, aerial photographs and vegetative cover.  Establishment of the riparian habitat and the flood conveyance channel coefficient will be assessed through visual inspection and engineering judgment.

 

FUNDING

 

The City has two dedicated sources of fund for Performance Monitoring and Operations and Maintenance for the project.  First, the City’s Measure A allocations include the provision for use of Measure A proceeds during the 20-year tax and for the funding of a Maintenance Trust Fund to be established at year 2018 to provide for maintenance funds in perpetuity.  In addition, through its participation in the Countywide Flood Protection Maintenance Assessment program, which taxes all parcels for maintenance of the Napa River drainage system, there is an amount allocated for City of St. Helena drainage and flood projects.  The Maintenance Assessment has no sunset provision.  Between these two sources, the City has the financial ability to perform required maintenance.

 

MONITORING OF PHYSICAL FEATURES

 

In order to carry out the performance-based maintenance program, various physical features that affect performance in the Project reach will be monitored to identify changes. These features are hydrology, channel geometry, vegetation, and bank stability. Not all changes are considered detrimental; considerable reconfiguration of physical features may be allowed as long as they do not adversely affect conveyance (i.e., they do not decrease freeboard more than 10-50 percent upon prior approval from FEMA), bank stability, structural integrity, or habitat quality. In fact, significant evolution of the physical features is expected to occur following construction.

 

Performance monitoring of the EMP has been divided into the following categories:

 

·        Hydrology

·        Hydraulic Performance

·        Channel and Overbank Geometry

·        Vegetation, existing and new

·        Aquatic and Biotic Resources

 

The following sections present descriptions of design features of the EMP, monitoring methods to analyze feature performance and adaptive management measures to address potential concerns.

 

I.          Hydrology

 

Basic to the design and maintenance of all flood protection projects is the hydrology for the watershed being considered.  The Napa River watershed above the river reach of the EMP has been shown in recent years to be a relative “quick watershed.”  That is to say that the peak flow in the river generally occurs for a one-hour duration and approximately 2 hours after the peak rainfall in the upper watershed.  In the flood of 1986, rainfall duration was significantly longer and the peak river flows occurred slower remaining high for a longer period of time.  Although considerable rainfall and streamflow data is available downstream of this area, rather limited historical data is available that correlates rainfall to streamflow upstream.

 

In 1997, the Napa County Flood Control and Water Conservation District (FCD), in cooperation with the cities of Napa, St. Helena, Calistoga and Yountville, installed additional rainfall and streamflow monitoring equipment into what is called an ALERT monitoring system.  The ALERT system supplemented the existing network of five rainfall stations and two streamflow stations installed and maintained by the USGS and DWR in cooperation with FCD.  The ALERT system provides the data through radio waves, which are received at various locations within the County.  The data is also collected by a consultant that provides a visual representation for the agencies and make the data available through an Internet connection for public use. 

 

The system was installed for two primary purposes:

 

·        Assist communities in their flood forecasting activities; and

·        Provide data necessary for design and monitoring of future flood protection and environmental enhancement projects.

 

Goals

 

A key goal is to develop a data set to gain a more thorough understanding of the hydrology of the Napa River within the project reach. Specifically, the hydraulic capacity of the project reach at different stages is of primary importance to validating the modeling assumptions of the design and for establishing the performance of the project. Therefore, the goal is to collect high water mark data for known discharges along the project reach.

 

Monitoring Methods

 

This data can now be used to estimate the flow for each storm that occurs in the watershed and then correlated to the visual conditions through the reach of the EMP.  As discussed in the following section on Hydraulic Performance, this correlation will be important in analyzing the performance of project features compared to project objectives.  The analysis will assist in identifying potential areas of concern that can lead to preventive maintenance measures.

 

Adaptive Management Measures

 

The ALERT system requires annual and periodic maintenance to assure proper performance and accuracy.  The City of Napa, Department of Public Works provides the annual maintenance of the monitoring equipment under a memorandum of understanding with FCD and the respective agencies.  Maintenance has been conducted by Napa for the last five years and includes:  cleaning, calibration and replacement of equipment.  The City of St. Helena, under recommendation by their consultant, is planning the enhancement of the existing network with the installation of additional streamflow gauges and the relocation of the existing St. Helena Stream Gauge at Zinfandel Lane in cooperation with the FCD, USGS and DWR.  Annual and periodic maintenance of the data delivery and archives is provided under contract with Diad, Incorporated.  These activities will continue to be supported by St. Helena and the other agencies under joint agreement.

 


II.        Hydraulic Performance  

 

Based upon the hydrologic data collected in paragraph I above, the hydraulic performance of project features over a range of flows can be analyzed and evaluated for hydraulic performance. Actual hydraulic performance helps account for a complex set of assumptions that have to be made in project design and modeling. The range of flows of interest includes large floods up to 100-year peak design flow down to the 500 cfs range to assess geomorphic processes in and around the low flow channel.  Hydrologic data provided by the ALERT system will be valuable in analyzing the hydraulic performance of the EMP.

 

Goals

 

Maintain as close to a 100-year flood capacity, with an additional three feet of freeboard, in the project reach of the Napa River as possible without compromising the ecological restoration goals of the project. This will be accomplished by initially maintaining the desired vegetation cover through vegetation management and its assumed hydraulic roughness and then as data collection advances, vegetation cover would be adjusted to actual hydraulic performance.

Monitoring Methods

 

Flow levels will be monitored by several methods in order to evaluate hydraulic performance. The effort will be geared toward developing a reliable hydraulic model of the project in order to compare predicted modeling with actual performance results. Integration of hydraulic performance monitoring with the topographic surveys and vegetation cover is an essential requirement.

 

Within the project a set of water level recorders and crest gages will be established under consultation with MBK Engineers and David Ford Consulting Engineers. These devices will allow for continuous water surface measurements and peak water stages at various locations in the project reach. These devices should be supplemented with field high watermark surveys after known floods or during actual flows when conditions allow for safe access.

 

The data collection frequency should be intensive just after construction in order to establish water surface / discharge relations over a range of flows in the channel, at the inlets of overflow channels and in the overbank areas. As data is compiled, levels will be monitored to see if flood capacity objectives are being met and if any topographic changes are creating problems.

Adaptive Management Measures

 

Measures have been taken during project design to create a self-maintaining project that after the initial vegetation establishment period, will require little if any maintenance. However, Ppotential concerns would arise if the flood capacity is reduced below the design level or if geomorphic stability is compromised. These problems could occur due to sediment deposition, erosion, topographic changes, higher than expected hydraulic roughness, or differences between actual flow capacity and hydraulic modeling predictions.

 

A thorough alternative assessment should be undertaken if in the unlikely event flood capacity is reduced below the design level or geomorphic stability is compromised and   changes are necessary, such as removal of sediment or vegetation or increasing the height of levees or floodwalls. The project has been designed to include 3 feet of freeboard on levees and floodwalls above calculated 100-year peak flood water surface elevations; this must be maintained to retain FEMA certification. Vegetation shall not be disturbed or removed any more than necessary to maintain the flood protection goals of the project.  If it is determined that the capacity for the design 100-peak year flood protection goal has not been met, a range of options should be assessed, including a no-action plan to accept a lower flood capacity.

 

Other measures might be taken if hydraulic performance does not produce anticipated ecological benefits. This might include regrading and revegetating areas where conditions have not resulted in successful plantings, for example. Or there may be a need to reduce or increase the frequency of overbank flow. Resource agencies would be consulted and required permits/approvals obtained prior to implementation of any of these measures. The annual inspections will be correlated with the hydrological data to analyze potential modifications to construction features of the EMP.

 

III.       Channel and Overbank Geometry

 

Much of the project success will depend upon maintenance of the project area topography within an acceptable range of elevations to achieve flood capacity objective of containment of a 100-year flood. Topography will dictate flood capacity to a great extent and can be an influence on geomorphic stability and processes.

 

The nature of deposited sediments is of great interest to many aspects of the project, including sediment deposition as it affects flood capacity, mineral soils for native plant colonization, etc. The size of bedload transport deposited in the channel will help determine the quality of aquatic habitat and whether there is a trend in bedload deposits that might bear upon channel stability.

 

Monitoring and management of erosion problems is an important component of the adaptive management plan. It is anticipated that the Napa River will have an expanded area within which to meander without impacting property or structures. The final design of the EMP will include tolerances for lateral erosion of the channel before action is necessary to control erosion. Other potential erosion areas might occur at the outer edges of the flood channels. The boundaries of erosion will be established during the design process, but will likely be the projected 1 vertical: 1.5 horizontal plane from the base of floodwalls, levees or the designated edges of properties and infrastructure. These areas and erosional limits will be precisely designated on the project plans.

 

Goals

 

Maintain slope ratios from the base of floodwalls, levees or the designated edges of properties and infrastructure as selected during final design to the extent possible.

 

Monitoring Methods

 

Topographic cross sections will be established across the project site after construction. An as-built topographic survey shall document post-construction topography. The density of the cross sections should be adequate to construct a hydraulic model, or approximately one cross-section every 300 feet, and should extend from the edges of the flood plain through the channel.  River cross sections currently identified as critical for the monitoring the performance of the EMP will be labeled upon final design and include:

 

·        The Pope Street Bridge, immediately upstream and downstream

·        The gravel bar in the river at the confluence with Sulphur Creek

·        The “point” in the area of the existing riprap

·        The outlets to the east and west overflow channels

·        The inlets to the east and west overflow channels

·        The Pratt Street Bridge, immediately upstream and downstream

 

The baseline survey will be used to construct a hydraulic model of the project in conjunction with the hydraulic roughness data input from the vegetation surveys. The cross sections will be surveyed annually until it is deemed by the City and in consultation with resource agencies that less frequency is required. There should be a focus on surveys after major flood events (greater than 10-year peak flow) when topographic changes might be greatest.

 

Just after construction and once every five years a full topographic survey of the project site will be undertaken using a combination of ground surveys (in areas covered by vegetation) and aerial surveys.  A 2-foot contour interval should be adequate in most open areas. The aerial should have an underlying ortho-rectified color aerial photograph.  The City will also assess frequency of this monitoring after the first five-year interval.

 

A field survey of the longitudinal profile of the channel will be measured every five years after construction.  Upon completion of the ten-year survey, the City will assessed the necessity for future surveys.  The longitudinal profile will measure streambed thalweg, water surface, bankfull features, and any high water lines. The data will be managed for assessment by the project geomorphologist for an annual review and presentation.

 

Sediment data will be collected in the channel and on the flood plain surfaces using standard pebble count and surface sampling collecting methods. Channel sampling should include pebble counts in the channel in a consistent geomorphic location, sampling of sub-surface layers below the channel bed, and sampling of newly deposited sediments on the banks (i.e. bankfull sediments). The samples should be analyzed for grain sizes and the sample locations mapped.

 

Sediment deposits in flood plain areas will be mapped and sampled. The fresh deposits will be mapped annually on the most recent aerial photographs and will include the lateral extent of the deposit as well as the depth. A sample will be taken of selected deposits for grain size analysis.

 

The channel and designated erosional limit areas will be inspected annually for any problems, such as new or progressing erosion that could potentially progress into an established “no erosion” zone. The inspections will be visual, but will also include examination of aerial photos and topographic surveys in order to determine any trends.

 

Adaptive Management Measures

 

The topographic cross sections and maps will be compared by a geomorphologist with previous surveys in order to assess changes and make recommendations, if necessary. The key areas of concern are: aggradation of the channel with coarse bedload to a degree that could impair flood capacity (see hydraulic performance above) or channel stability and aggradation of the overbank flood channels or created flood plain. The monitoring data will also reveal problems with full spanning logjams that inhibit fish passage or might pose a threat to lateral channel stability. The project geomorphologist should make recommendations to rectify any problems in consultation with the City and appropriate agencies.

 

It is anticipated that the EMP project will actually reduce erosional forces along the channel rather than increase the hazards. Subsurface explorations have revealed that the soils are relatively cohesive and strong and able to hold steep slopes. They also erode slowly, which may partially explain the long-term stability. However, erosion must be taken seriously as a future project maintenance issue.

 

The process for addressing erosion problems will be highly proactive under the adaptive management plan. First, the monitoring program will reveal potential problems early so that low-tech, vegetative methods will be employed to slow down or eliminate erosion. If the problem(s) become severe enough to warrant structural treatment, then a design process will be initiated.

 

The design process will include identification of a range of treatment options emphasizing bioengineered methods to create opportunities for habitat development. The proposed alternatives would be made available to resource agencies and the City for consideration and selection of a preferred plan. TAgain, the emphasis will be to treat erosion problems as early as possible with vegetative techniques to minimize any need for the cost and potential effects of structural bank protection.

 

An example of a bank protection alternatives document has recently been completed for a location at the confluence of Sulphur Creek and the Napa River where a failure occurred in 1998. This site is being considered for repair prior to construction of the floodwall included in the EMP. The alternative plans range from no action to full revetment with several different options in between. The report describing these options is included as Appendix C to the revised draft EIR.

 

IV.       Vegetation, Existing and New

 

The vegetation planting component is a key element of the project as it is anticipated to provide soil and channel stability and habitat value. The specific objective is to achieve the vegetation cover shown on the planting plan presented in the revised draft EIR. It may become necessary to modify the plan during the design and engineering phase and perhaps during project life if post-project conditions are different than those anticipated in the original design. The following monitoring and maintenance plan is designed to collect the data necessary to determine if success is being achieved and if adjustments are necessary.

 

Monitoring

 

The initial 5-year establishment period will involve intensive efforts to establish native plantings and to have native plantings out-compete undesirable invasive non-natives (i.e. arundo donax, etc.). A specific revegetation plan will be prepared for construction with the details of design, planting species, densities, irrigation and performance. Carrying out the revegetation plan will be the responsibility of the landscape contractor; however it will be important to ensure that it is directed to meet ecosystem and EMP goals.

 

Goals

 

Maintain vegetation in the terraces according to the Vegetation Establishment Plan that 1) meets the roughness criteria needed to provide as close to 100-year flood protection as possible, 2) stabilizes soils, and 3) provides suitable habitat for target species in the project reach. 

 

 

Monitoring

 

Prior to construction, vegetation transects will be established to measure pre-project conditions. These will be used to compare future post-project conditions. After construction and during the establishment period, the monitoring transects will be established at the same locations as the pre-project locations and will coincide with some of the topographic cross sections (described above) and shallow groundwater monitoring wells. The groundwater wells will be arrayed along three selected cross sections to document the gradient of water levels in the plant rooting zones.

 

Annual surveys of plant communities will be measured to document plant development, species composition and diversity. There are several methods for developing annual plant databases in a statistically meaningful way.

 

The overall plant cover will be mapped by plant community cover type every two years using the most current color photographic survey. This will allow for collection of time-sequenced data that can be incorporated into a GIS database for quantitative comparison to the original plan. The survey will also serve to develop a biannual maintenance plan to replace failed plantings, to tag areas for removing exotic vegetation, or other actions. The survey should be conducted at least twice in the first five years as part of the landscape installation contract and, thereafter, as often as it is deemed appropriate to properly monitor the plantings.

Adaptive Management Measures

 

Based upon the monitoring results, the project vegetation specialist may determine that modifications to the original revegetation plans are in order due to different or changing conditions. For example, there may be natural native plant colonization that occurs that is different than prescribed by the planting plan. Or there might be areas subject to frequent scour or too dry to support the intended vegetation cover. The vegetation specialist should propose a modified cover that complies with flood capacity objectives and the goals set by the regulatory agencies.

 

V.        Aquatic and Biotic Resource Conditions

 

A key component of the EMP project is to achieve significant ecosystem restoration for the project reach and avoid impacts to wildlife during operation of the project. The success of the project will be assessed through direct measurement of wildlife populations and habitat usage. 

Goals

 

Maintain and enhance wildlife populations, including special status species, in the project reach of Napa River.

Monitoring Methods

 

The success of the project will be assessed through direct measurement of wildlife populations and habitat usage.  Standard wildlife habitat survey methods will be employed the project wildlife biologist to document pre- and post-project wildlife populations. The methods include visual surveys of birds, aquatic, terrestrial and amphibious wildlife and trapping for species that provide food for higher mammals and raptors. Surveys for aquatic species include diving and electroshock population surveys for fish and sampling of aquatic insects. A specific set of objectives for wildlife populations (more specific than “maximizing”) will be established after the baseline survey of existing resources and examination of the final EMP project. The same methods for monitoring surveys will be used during annual inspections.

 

After flood events the City will monitor the terraces to check for stranding of fish and other impacts to wildlife. 

Adaptive Management Measures

 

Post-flooding, Wwildlife population surveys alongside and plant surveys will be used as a tool to measure the success of ecosystem restoration and of avoiding impacts to wildlife during project operation. The wildlife biologist(s) shall make recommendations for the improvement of the ecosystems and the avoidance of operational impacts on wildlife within the project area based on survey results.  The potential measures that will be employed to enhance wildlife population include removal of exotic species and predators (e.g. cowbirds and feral cats), installation of nesting boxes, modification of plant communities or topography to favor habitat for selected species, management of woody debris in on the sides of the channel to favor development of desired aquatic habitat, or manipulation to improve amphibian habitat.  If impacts to wildlife occur during flooding events, design modifications to the terraces and/or appropriate response methods may be considered.

 

SUMMARY OF ADAPTIVE MANAGEMENT PLAN

 

This draft Adaptive Management Plan is a performance-based operation and maintenance manual for the Enhanced Minimum Plan as presented in the St. Helena Comprehensive Flood Study.  Its finalization will occur after:

 

·        Certification of the final EIR

·        Selection of a project by the City Council

·        Design of that project

·        Construction of the project

 

It will be prepared in consultation with Regional Water Quality Control Board, the United State Army Corps of Engineers, Department of Fish and Game, United States Fish and Wildlife Service, NOAA Fisheries and Federal Emergency Management Agency.  The plan will be adapted to the future monitoring of project features and their performance in obtaining the objectives of the project.

 

The following table is presented as a summary of this plan to date that will serve the City as a checklist of periodic monitoring and maintenance activities.